TY - GEN
T1 - Decommissioning the BELGONUCLEAIRE Dessel MOX plant
T2 - 2013 - ICEM
AU - Cuchet, Jean-Marie
AU - Libon, Henri
AU - Verheyen, Carlo
AU - Bily, J.
AU - Boden, Sven
AU - Joffroy, F.
AU - Walthéry, Robert
N1 - Copyright © 2013 by ASME.
PY - 2013
Y1 - 2013
N2 - BELGONUCLEAIRE has been operating the Dessel MOX plant at an industrial scale between 1986 and 2006. During this period, 40 metric tons of plutonium (HM) have been processed into 90 reloads of MOX fuel for commercial light water reactors. The decision to stop the production in 2006 and to decommission the MOX plant was the result of the shrinkage of the MOX fuel market due to political and commercial factors. As a significant part of the decommissioning project of the Dessel MOX plant, about 170 medium-sized glove-boxes and about 1.200 metric tons of structure and equipment outside the glove-boxes are planned for dismantling. The license for the dismantling of the MOX plant was granted by Royal Decree in 2008 and the dismantling started in March 2009. The dismantling works are carried out by an integrated organization under leadership and responsibility of BELGONUCLEAIRE; this organization includes 3 main contractors, namely Tecnubel N.V., the THV ('Tijdelijke HandelsVereniging') Belgoprocess / SCK·CEN and Studsvik GmbH and TRACTEBEL ENGINEERING as project manager. In this paper, after having described the main characteristics of the project, the authors review the different organizational and technical options considered for the decommissioning of the glove-boxes; thereafter the main decision criteria (qualification of personnel and of processes, confinement, cutting techniques & radiation protection, safety aspects, alpha-bearing waste management) are analyzed as well. Finally the progress, the feedback and the lessons learned at the end of August 2013 are presented, giving the principal's and contractors point of view.
AB - BELGONUCLEAIRE has been operating the Dessel MOX plant at an industrial scale between 1986 and 2006. During this period, 40 metric tons of plutonium (HM) have been processed into 90 reloads of MOX fuel for commercial light water reactors. The decision to stop the production in 2006 and to decommission the MOX plant was the result of the shrinkage of the MOX fuel market due to political and commercial factors. As a significant part of the decommissioning project of the Dessel MOX plant, about 170 medium-sized glove-boxes and about 1.200 metric tons of structure and equipment outside the glove-boxes are planned for dismantling. The license for the dismantling of the MOX plant was granted by Royal Decree in 2008 and the dismantling started in March 2009. The dismantling works are carried out by an integrated organization under leadership and responsibility of BELGONUCLEAIRE; this organization includes 3 main contractors, namely Tecnubel N.V., the THV ('Tijdelijke HandelsVereniging') Belgoprocess / SCK·CEN and Studsvik GmbH and TRACTEBEL ENGINEERING as project manager. In this paper, after having described the main characteristics of the project, the authors review the different organizational and technical options considered for the decommissioning of the glove-boxes; thereafter the main decision criteria (qualification of personnel and of processes, confinement, cutting techniques & radiation protection, safety aspects, alpha-bearing waste management) are analyzed as well. Finally the progress, the feedback and the lessons learned at the end of August 2013 are presented, giving the principal's and contractors point of view.
UR - http://www.scopus.com/inward/record.url?scp=84900660039&partnerID=8YFLogxK
U2 - 10.1115/ICEM2013-96020
DO - 10.1115/ICEM2013-96020
M3 - In-proceedings paper
AN - SCOPUS:84900660039
SN - 9780791856024
VL - 2
T3 - Proceedings of the International Conference on Radioactive Waste Management and Environmental Remediation, ICEM
BT - ASME 2013 15th International Conference on Environmental Remediation and Radioactive Waste Management, ICEM 2013
PB - ASME - The American Society of Mechanical Engineers
Y2 - 8 September 2013 through 12 September 2013
ER -